§ 108.4.3. Concrete slab or under-floor inspection.  


Latest version.
  • Inspection shall be made after all in-slab or under-floor reinforcing steel, building service equipment, conduit, piping accessories and other ancillary equipment items are installed but before any concrete is poured or floor sheathing installed, including the subfloor.

(Ord. 2002-0076 § 41, 2002: Ord. 95-0065 § 3 (part), 1995.)