§ 108.4.2. Foundation inspection.  


Latest version.
  • Inspection shall be made after excavations for footings is complete and any required reinforcing steel is in place. For concrete foundations, any required forms shall be in place prior to inspection. All materials for the foundation shall be on the job site; however, where concrete is ready mixed in accordance with approved nationally recognized standards, the concrete need not be on the job site. Where the foundation is to be constructed of approved treated wood, additional inspections may be required by the Building Official.

(Ord. 2002-0076 § 40, 2002: Ord. 95-0065 § 3 (part), 1995.)