§ 2.202.040. Debarment of contractors.  


Latest version.
  • A.

    The county may debar a contractor who has had a contract with the county in the preceding three years and/or a contractor who has submitted a bid or proposal for a new contract with the county.

    B.

    The county may debar a contractor if the county finds, in its discretion, that the contractor has done any of the following: (1) violated a term of a contract with the county or a nonprofit corporation created by the county; (2) committed an act or omission which negatively reflects on the contractor's quality, fitness, or capacity to perform a contract with the county, any other public entity, or a nonprofit corporation created by the county, or engaged in a pattern or practice which negatively reflects on same; (3) committed an act or omission which indicates a lack of business integrity or business honesty; or (4) made or submitted a false claim against the county or any other public entity.

    C.

    The decision by the county to debar a contractor is within the discretion of the county. The seriousness and extent of the contractor's acts, omissions, patterns, or practices as well as any relevant mitigating or aggravating factors, including those described in Subsection (E) below, may be considered by the county in determining whether to debar a contractor and the period of debarment. Generally, the period of debarment should not exceed five years. However, if circumstances warrant, the county may impose a longer period of debarment up to and including permanent debarment.

    D.

    To impose a debarment period of longer than five years, and up to and including permanent debarment, in addition to the grounds described in Subsection (B) above, the county shall further find that the contractor's acts or omissions are of such an extremely serious nature that removal of the contractor from future county contracting opportunities for the specified period is necessary to protect the county's interests.

    E.

    Mitigating and aggravating factors that the county may consider in determining whether to debar a contractor and the period of debarment include but are not limited to:

    (1)

    The actual or potential harm or impact that results or may result from the wrongdoing.

    (2)

    The frequency and/or number of incidents and/or duration of the wrongdoing.

    (3)

    Whether there is a pattern or prior history of wrongdoing.

    (4)

    A contractor's overall performance record. For example, the county may evaluate the contractor's activity cited as the basis for the debarment in the broader context of the contractor's overall performance history.

    (5)

    Whether a contractor is or has been debarred, found non-responsible, or disqualified by another public entity on a basis of conduct similar to one or more of the grounds for debarment specified in this Section.

    (6)

    Whether a contractor's wrongdoing was intentional or inadvertent. For example, the county may consider whether and to what extent a contractor planned, initiated, or carried out the wrongdoing.

    (7)

    Whether a contractor has accepted responsibility for the wrongdoing and recognizes the seriousness of the misconduct that led to the grounds for debarment and/or has taken corrective action to cure the wrongdoing, such as establishing ethics training and implementing programs to prevent recurrence.

    (8)

    Whether and to what extent a contractor has paid or agreed to pay criminal, civil, and administrative liabilities for the improper activity, and to what extent, if any, has the contractor made or agreed to make restitution.

    (9)

    Whether a contractor has cooperated fully with the county during the investigation, and any court or administrative action. In determining the extent of cooperation, the county may consider when the cooperation began and whether the contractor disclosed all pertinent information known to the contractor.

    (10)

    Whether the wrongdoing was pervasive within a contractor's organization.

    (11)

    The positions held by the individuals involved in the wrongdoing.

    (12)

    Whether a contractor participated in, knew of, or tolerated the offense.

    (13)

    Whether a contractor brought the activity cited as a basis for the debarment to the attention of the county in a timely manner.

    (14)

    Whether a contractor has fully investigated the circumstances surrounding the cause for debarment and, if so, made the result of the investigation available to the county.

    (15)

    Whether a contractor had effective standards of conduct and internal control systems in place at the time the questioned conduct occurred.

    (16)

    Whether a contractor has taken appropriate disciplinary action against the individuals responsible for the activity which constitutes the cause for debarment.

    (17)

    Other factors that are appropriate to the circumstances of a particular case.

    F.

    Before making a debarment determination pursuant to this chapter, the department head shall give written notice to the contractor of the basis for the proposed debarment, and shall advise the contractor that a debarment hearing will be scheduled on a date certain. The contractor hearing board shall conduct a hearing where evidence on the proposed debarment is presented. The contractor and/or attorney or other authorized representative must be given an opportunity to appear at the debarment hearing and to submit documentary evidence, present witnesses, and offer rebuttal evidence at that hearing. After such hearing, the contractor hearing board shall prepare a proposed decision, which shall contain a recommendation regarding whether the contractor should be debarred and, if so, the appropriate length of time for the debarment. A record of the hearing, the proposed decision, and any recommendation shall be presented to the board of supervisors. The board of supervisors may, in its discretion, limit any further hearing to the presentation of evidence not previously presented. The board of supervisors shall have the right to modify, deny, or adopt the proposed decision and recommendation of the contractor hearing board. A debarment finding shall become final upon the approval of the board of supervisors.

    G.

    In making a debarment determination, the board of supervisors may also, in its discretion and consistent with the terms of any existing contracts that the contractor may have with the county, terminate any or all such existing contracts. In the event that any existing contract is terminated by the board of supervisors, the county shall maintain the right to pursue all other rights and remedies provided by the contract and/or applicable law.

    H.

    With respect to a contractor who has been debarred for a period longer than five years, the contractor may, after the debarment has been in effect for at least five years, request that the county review the debarment determination to reduce the period of debarment or terminate the debarment. The county may consider a contractor's request to review a debarment determination based upon the following circumstances: (1) elimination of the grounds for which the debarment was imposed; (2) a bona fide change in ownership or management; (3) material evidence discovered after debarment was imposed; or (4) any other reason that is in the best interests of the county. A request for review shall be in writing, supported by documentary evidence, and submitted to the chair of the contractor hearing board. The chair of the contractor hearing board may either: 1) determine that the written request is insufficient on its face and deny the contractor's request for review; or (2) schedule the matter for consideration by the contractor hearing board which shall hold a hearing to consider the contractor's request for review, and, after the hearing, prepare a proposed decision and a recommendation to be presented to the board of supervisors. The board of supervisors may, in its discretion, limit any further hearing to the presentation of evidence not previously presented. The board of supervisors shall have the right to modify, deny, or adopt the proposed decision and recommendation of the contractor hearing board. A reduction of the period of the debarment or termination of the debarment shall become final upon the approval of the board of supervisors.

(Ord. 2014-0035 § 4, 2014: Ord. 2005-0066 § 4, 2005: Ord. 2004-0009 § 3, 2004: Ord. 2000-0011 § 1 (part), 2000.)