J105.7 - Required inspections.  


Latest version.
  • The permittee shall call for an inspection by the Building Official at the following various stages of work and shall obtain the approval of the Building Official prior to proceeding to the next stage of work:

    Pre-grade. Before any construction or grading activities occur at the site. Permittee shall schedule a pre-grade inspection with the Building Official. The permittee shall ensure that all project consultants are present at the pre-grade inspection.

    Initial grade. When the site has been cleared of vegetation and unapproved fill and has been scarified, benched, or otherwise prepared for fill. No fill shall have been placed prior to this inspection.

    Rough grade. When approximate final elevations have been established, drainage terraces, swales, and other drainage devices necessary for the protection of the building sites from flooding have been installed, berms have been installed at the top of the slopes, and the statements required by Section J105.12 have been received.

    Final grade. When grading has been completed, all drainage devices necessary to drain the building pad have been installed, slope planting has been established, irrigation systems have been installed, and the as-built plans and required statements and reports have been submitted.

(Ord. 2016-0053 § 109, 2016.)