§ 20.36.120. Successor in interest—New permit required.  


Latest version.
  • The successor in title or interest of a premises for which a permit had previously been granted shall file with the director a new permit application, in accordance with the provisions of Section 20.36.320 or Section 20.36.490, within 30 days after assumption of such title or interest, and shall furnish plans and data as may be required by the director. If it appears from the application, data, and/or inspection of the facility that the succeeding operation and disposal practices comply with the provisions of this Division 2, the director, upon receipt of the fees hereinafter required, shall issue such permit. The director may issue an interim permit pursuant to Section 20.36.125 to allow continued operations during the permit processing period.

(Ord. 2002-0074 § 1, 2002: Ord. 89-0101 § 28, 1989.)