§ 20.32.130. Connection charges—Designated.  


Latest version.
  • A.

    No permit shall be issued for the direct connection of any lot to a public sewer which has been constructed at no cost to such lot, or to a trunk sewer in which capacity has been assigned by the owner thereof to the county of Los Angeles until, in addition to any other fees required by this Division 2 and by the Plumbing Code set out at Title 28, there has been paid a connection charge in an amount equal to $12.00 per front foot of the lot sought to be connected if said lot is rectangular and has an average depth of 100 feet or more. If the shape of lot is other than the usual rectangular shape, or unusual in area, and the strict adherence to the above mentioned provision would require payment of an amount not commensurate with the benefits to be received, the provisions of this section as to the amount to be charged may be modified as determined by the county engineer. In no case shall the charge be less than $300.00, unless reduced by the charges of another public entity as provided in Section 20.32.160.

    B.

    Property owned by a public entity and being used by such entity in the performance of a governmental function is exempt from the requirements of this section.

(Ord. 81-0043 § 1, 1981: Ord. 11716 § 17, 1978: Ord. 10020 § 3 (part), 1970: Ord. 7314 § 3, 1958: Ord. 6130 Part 5 Ch. 2 § 5204, 1952.)